For the previous week, I have updated the track to incorporate the changes with the bracket changes that have been done. I made three different assemblies that will make putting the track together easier in terms of mating on Solidworks. There are three assemblies: station, corner, and loop connector. These assemblies consist of both top and bottom rails. Pictures are shown below of the progress. Also some time has been put into updating the power point to get ready for presentations for today.
Wednesday, October 26, 2016
Wednesday, October 19, 2016
Full Track Assembly
This week I was able to fully assemble the track which will be shown in figure 1. I still need to run finite element analysis in order to understand how deformations will happen and where support posts will be needed the most. I also did FEA on the U-bracket we designed to see how it would perform which is shown in figure 2. From what it looks, the way it is currently mounted would cause one side to have more stress. We might have to consider another way to mount these brackets. For both track and U-bracket, aluminum 6061 was used to run the test. One thing that has not been looked into is other material use. I've looked into it briefly but have not read enough to actually make comparisons.
Figure 1: Full track assembly
Figure 2: FEA on U-Bracket
Wednesday, October 12, 2016
Progress 10/12/16
This week was quite slow for us. Due to presentations and midterms, I was not able to work on the project as much. I will soon post the updated track layout in the 12th scale archive so others will have access to it. One thing that needs to be worked on is running FEA so we can determine if the track layout has sufficient stand support. Once FEA is done, we should be getting into our rapid prototyping.
Wednesday, October 5, 2016
Progress 10/5/2016
For this week, I worked on designing a bracket that will help keep the width of the track uniform at the end of the bends. We noticed that the width vary through out the track causing the bogie to work more at tighter widths. These brackets are meant to be welded on instead of screwed in. I also worked on getting a two loop track together but the connector between loops is not done yet. Pictures of CAD work is shown below.
Figure 1: ISO view of bracket
Figure 2: Dimensions of bracket
Figure 3: Two loop Track
Subscribe to:
Posts (Atom)